|
Trustees
approve utilities upgrade
By Kim Billings, Media
Relations
The University System of New Hampshire Board of Trustees last week
authorized UNH to upgrade the current heating plant and related
facilities on the Durham campus -– a plan that is projected
to avoid energy costs of $35 million over the next 20 years.
A $28 million cogeneration plant will be financed through a combination
of an internal loan and a capital lease, according to Candace Corvey,
UNH vice president for finance and administration.
“Most of the cost of this project is in equipment that can
be externally financed through a capital lease, thus reducing our
need to draw upon scarce internal resources.”
“The plan is essential in order to meet the campus’s
need for more energy, maximize reliability, promote a cleaner environment,
and contain costs,” explains Allan Braun, associate vice president
for facilities at UNH.
The many benefits that will be realized by UNH in taking a comprehensive
approach to heating, cooling and electrical needs on campus provides
a strong example of effective use of limited resources to maximize
operating efficiency, says Ed MacKay, USNH vice chancellor and treasurer.
“The financing of the utility upgrade plan is an example of
the university system’s willingness to engage in ‘self-help’
to fund the majority of its capital investment needs,” MacKay
explains. “State appropriation support is focused almost exclusively
on capital projects that directly impact student learning, such
as academic buildings, labs and lecture halls. We leverage our assets
to fund other capital projects -– using the Health and Education
Finance Authority (HEFA) bonds for self-supporting projects such
as residence and dining halls; federal grants for research facilities,
and; private gifts and operating budgets for ongoing improvements
in the physical plant.”
UNH officials say the existing central steam heating plant has reached
capacity. Without the cogeneration project, the capital cost of
adding future heating capacity through 2016 is estimated to be $17
million. Chilled water requirements necessary for air conditioning
for research purposes would add another $7.8 million.
In addition, the electrical requirements at UNH are far outpacing
the electrical infrastructure. Two substations are 40 years old,
and another will need to be replaced within 10 years. Replacement
costs for the substations is $450,000.
Braun says the cogeneration process is highly efficient, because
it generates electricity with hot gas turbines that, as a byproduct,
produce waste heat. That heat is used to produce steam and chilled
water (necessary for air conditioning) at very low cost. This approach
provides energy flexibility, as the plant could utilize #6 oil,
#2 oil, natural gas, or external electricity depending on the relative
cost and availability of each.
He notes the university has been exploring various options for its
Utility Master Plan over the past three years. After completion
of a comprehensive feasibility study, and many conversations with
stakeholders, UNH officials concluded that a cogeneration plant
was the best option.
Braun adds that cogeneration is environmentally friendly and very
safe.
The plant -– which would be located beside the current heating
plant behind the Service Building -- is estimated to cost $22 million
to construct and equip. UNH also would build a chiller node (needed
for air conditioning) near Philbrook Dining Hall for roughly $6
million in order to provide chilled water to eight surrounding buildings.
The plant and the chiller node will be constructed to enable additional
generating, chilled water, and heating capacity to be added as the
university’s physical plant grows.
The plant and the chiller node are expected to be on line and operational
by the fall of 2005. The plant will be operated by a private company,
EMCOR, under a contract closely managed by UNH. The contract will
provide incentives for EMCOR to operate the plant efficiently and
effectively.
|