Material
availability and low costs for reactive barrier
caps are central to their consideration for
any capping project. The current sources for
phosphorite rock materials on the Eastern United
States include PCS Phosphates in North Carolina
and IMC-Agrico in Florida. Both the Phosfil
product available from PCS Phosphates and the
Florida phosphorite rock can be purchased for
approximately $135/ton, which includes delivery
by truck within 400 miles of the source. Work
on the Anacostia River required 235 tons of
phosphorite rock to cap the 743 m2 area. Based
on the above prices the cost of the Phosfil
barrier material delivered was $31,725. In the
future, there are several factors that may work
to reduce this price including shipping materials
by ocean barge, larger volume production, and
improved deployment techniques to minimize material
waste.
In 1997 the District of Columbia
commissioned a study to determine the extent
of contamination, remediation options, and cost
associated with the Anacostia River (Velinsky,
et al., 1997). This study determined the area
and volume of contaminated sediments present
in the Anacostia River, and the adjacent Washington
Channel. Additionally the study estimated the
costs required for four conventional remediation
scenarios. Our research has expanded these four
scenarios to include cost estimates and potential
benefits for four additional phosphate-based
reactive barrier capping systems (Figures 1
and 2).
To generate these cost estimates,
the following facts and assumptions were
used.
- The availability of dredge
sediment disposal space is highly limited.
The first 250,000 yd3 would be used by the
US ACE on the Kingman Lake project, and would
cost only $5/yd3. The location of the site
would require that additional dredged materials
would need to be transported up to 50 miles
away to the next available facility (although
no facility large enough existed in the area
at the time).
-
Dredging of the area assumes two scenarios.
First clean dredging using a hydraulic
dredge with high precision and low unwanted
sediment transport would cost about $15/yd3.
Lower cost hydraulic dredging could be implemented
for $5/ yd3 but with high offsite sediment
transport.
- A transport system is
assumed for suctioning the dredged materials
via a pipeline to a disposal/transfer facility
within 3 km of the site.
- The costs for capping
and filling in the dredged areas were calculated
as ranging from $5-$7/yd2 for the clean sand
caps. This cost includes the purchase, delivery
and placement of the clean sand materials.
Clean sand materials being placed over the
reactive barriers require greater precision,
and were therefore calculated at a range of
$7-$10/yd2.
- The cost for the reactive
barrier cap material was estimated to be $15/yd2.
Assuming that the barrier was incorporated
into a geofabric mesh to ensure quick and
accurate deployment, the geofabric construction
is estimated at $12/yd2. Crane based deployment
of this system is estimated to cost an additional
$25/yd2, resulting in a total deployment cost
of $52/yd2. Large uncertainties in these numbers
means that a conservative pricing factor of
2x (or $104/yd2) was used as the high estimate
for reactive barrier deployment.
Scenarios
1 through 4 in Figure
1 (please click to see the full-size
figure) address contamination along the
entire length of the lower Anacostia River and
the WashingtonChannel (see Appendix A). Scenarios
5 through 8 in Figure 2 addresses contamination
in only the most polluted sections of the river.
Comparing capping costs between scenarios 2
and 3 (both of which deepen the channel by 1.25
ft.) it can be seen that the mid price for reactive
barriers are 33% lower. This cost savings comes
from two operational areas. First, less contaminated
material needs to be dredged in order to deepen
the channel to the same depth. This is a great
benefit, as disposal options in the Washington
D.C. area are extremely limited. The second
factor lowering costs is that less clean sand
is required on top of the reactive barrier material.
This is because the clean sand in a reactive
barrier only functions as a erosion and bioturbation
layer, but not a chemical migration barrier.
Comparing the costs
of remediation between scenarios 6 and 7 demonstrates
that even when only the "hot spots"
are treated, the reactive barrier system costs
45% less than the conventional barrier system.
Again, the costs of sediment disposal dominate
the overall operations costs. Since the only
300,000 yd3 of disposal space could be identified
in the Washington D.C. area for these sediments
during the original investigation. As a result,
it was concluded that no remediation could be
performed for a reasonable price. Table 1 summarizes
the quantities of sediments dredged and the
number of times above the disposal capacity.
Scenario 8 uses a reactive barrier to treat
the hot spots in the Anacostia River, does not
change the river depth, and allows for a remediation
option that fits within the current limited
disposal capacities of the Washington D.C. area.
This is not an option with any of the conventional
capping scenarios.
Table 1: Dredged Sediment Volumes
and Capacity Estimates
|
Scenario
|
Volume
Dredged (yd3)
|
Estimate Above
Disposal Capacity
|
|
1
|
10,935,775
|
36.5
|
|
2
|
3,645,258
|
12.2
|
|
3
|
2,733,944
|
9.1
|
|
4
|
1,093,577
|
3.6
|
|
5
|
2,530,884
|
8.4
|
|
6
|
843,628
|
2.8
|
|
7
|
632,721
|
2.1
|
|
8
|
253,088
|
0.8
|
Deployment of multiple layer
reactive barriers currently requires more handling
time, and higher labor costs than conventional
barriers. However, the relatively similar total
material costs (tons required*price per ton)
for phosphorite materials compared to conventional
barrier materials demonstrates that further
development of efficient deployment technologies
could result in an even more competitive capping
alternative.
Often, reactive barrier sediment
caps are more expensive than conventional capping
systems. However, from the above discussion
it can be seen that the use of phosphorites
as a reactive barrier offers several potential
economic benefits under different capping scenarios.
As disposal of contaminated sediments increases,
and viable disposal locations become scarce,
the thinner reactive barrier system becomes
more economically competitive against conventional
barrier systems.
References
Velinsky, D. J., Gruessner,
B., Haywood, H. C., Cornwell, J., Gammisch,
R. and Wade, T. L. (1997). Determination of
the Volume of Contaminated Sediments in the
Anacostia River; District of Columbia. Rockville,
MD, Interstate Commision on the Potomac River
Basin: 99.