|
Preliminary Boreholes : Phase II
During
Phase II of the Year I research, four preliminary boreholes will
be drilled with a direct rotary drill rig. Three of the preliminary
boreholes will be within the contaminant plume (i.e., TCE, DCE and
VC predominant zones of the plume). Past studies indicate that there
are zones of varying contaminant concentrations within the bedrock
(Weston, 1993).
Numerous bedrock wells have been installed at Pease Site 32. Weston
(1993) describes the telescoping casing used at Site 32 for installing
shallow bedrock wells. The telescoped casing is designed to isolate
the surficial lithology above the marine clay sediment layer from
the lithology below. (See Appendix D for discussion of the lithology
at Site 32.) The boreholes were started using a 14-inch casing,
which was telescoped to 8-inch down to bedrock.
The BBC's drilling will also be done using telescoping casing to
isolate the overburden and the shallow weathered bedrock zones from
the competent bedrock below. Drilling through the overburden will
commence using a 10-cm (4 in.) inside diameter (ID) hollow stem
auger. It is anticipated that the USGS will perform the overburden
drilling and sampling (See Appendix A USGS letter). Continuous
sampling of the overburden will be performed using a standard split
spoon sampler inside the casing. Typical depths of the overburden
at Site 32 are from 3 to 12 meters (Weston, 1993). The samplers
will be driven ahead of the 10 cm augers. Lexan liners will be used
in the split spoon, which will be sealed with caps and stored on
site for future reference. Samples will be screened for contaminants
using either a photoionization detector (HNU meter), or an organic
vapor analyzer (OVA). Those samples that emit organic vapors detected
by the meters will be handled as hazardous waste. Drilling will
be halted once the weathered bedrock zone has been encountered.
The auger hole will be grouted up to the surface with a cement and
bentonite grout as the augers are withdrawn from the borehole. Sampling
boreholes will be drilled and grouted at all four preliminary well
sites.
A second subcontractor (to be selected based on bids) will be brought
in to drill down through the overburden with a 30.5-cm (12-inch)
casing. The borehole will extend at least 30 cm into the weathered
bedrock. The 30.5-cm casing will then be pressure grouted in place,
such that grout will be forced up the annular space between the
casing and the outside of the borehole. This casing completion (grouting)
will essentially seal off the overburden, and the grout will displace
or stabilize contaminants that may have been in the borehole fluids.
Thirty-centimeter casings will be set within 3 meters of the exploratory
boreholes at each of the four preliminary well locations.
The remainder of the drilling will be done by the USGS (See Appendix
A USGS letter). The grout in the 30.5-cm casing will be drilled
out with a 25.4-cm bit, and a 20-cm casing will be extended down
to the weathered bedrock using a rotary wash technique. Direct rotary
wash will be used as opposed to air rotary techniques to prevent
the introduction of air into the subsurface, especially into bedrock
fractures. The drilling fluid used for the rotary wash drilling
will be clean formation water from on-site wells with similar water
chemistry to the water from the bedrock being drilled.
The weathered bedrock will be cored with an HQ (or smaller) wire-line
triple tube core barrel and a diamond coring bit. The HQ core barrel
will retrieve a 6 cm diameter core. Continuous cores will be taken
down to competent bedrock. It is anticipated, based on lithologic
studies at Site 32, that the weathered bedrock zone is less than
five meters. Clean formation water, obtained from an uncontaminated
well near Site 32, will be used to cool the coring bit. Once it
has been established that competent bedrock has been encountered,
the hole will be reamed with a 25.4-cm diameter bit using direct
rotary wash techniques.
The
water will be collected from a clean-on site well in a sterile polyethylene
truck-mounted tank the day before it is needed, and brought to the
drill site. The headspace in the tank will be filled with an inert
gas (argon) to minimize exposure to air and argon will be bubbled
through the water to remove oxygen if the borehole is anoxic or
suboxic. This procedure is specified because we are anticipating
low yields from appropriate on-site wells. Should an appropriate
supply well be found relatively close to the drill site which produces
sufficient water to match the drill rig demand, a direct connection
will be made to the drill rig, thus eliminating the need for the
tank. Clean pipe and hose will be used for this connection. The
chemical constituents in the drilling water will be monitored prior
to its use to be sure that it is similar to groundwater in the vicinity
of Site 32 (except for the lack of organic contaminants). A sample
of this water will also be taken and analyzed each drilling day.
The 20-cm casing will be advanced behind the drill bit used to
ream the hole through the weathered bedrock zone and at least 30
cm into competent bedrock. This casing will be grouted into place
to isolate the competent bedrock zone from the shallow weathered
bedrock. The casing will be drilled out down to the competent bedrock
once the grout has set. Coring will continue in the competent bedrock
to the design depth without additional casing (typically 50 meters
below ground surface (bgs)).
The competent bedrock will be continuously cored using a wire-line
HQ (or smaller) triple-tube core barrel with a diamond core bit,
similar to the weathered bedrock zone. The HQ core bit will leave
a 10 cm hole. Again, formation water from an on-site well will be
used as the drilling water as described previously. Samples of the
drilling water will be collected prior to drilling to evaluate the
potential for microbiological contamination of the formation and
the cores. The cores will be taken in 1.5 meter runs.
The first two cores from the first preliminary hole will be drilled
using conventional equipment and techniques, without special measures
to limit/prevent microbial contamination. The first day of coring
will use tracer-labeled drilling water. The first cores will be
withdrawn from the hole, and the core barrel transported directly
to the on-site anaerobic glove chamber, where the core will be extruded
under anaerobic conditions, as needed. The cores will be processed
for the presence of tracers (See Section VI.C). Heat sensitive tape
will be applied to the core barrel end bit to measure the maximum
temperatures achieved during drilling (Colwell et al., 1992).
Modified drilling procedures will also be tested in the first borehole
to evaluate their effectiveness. To prevent water from within the
core barrel from contaminating the core while it is still in the
barrel, a wax plug (seal) will be poured in the bottom of the core
barrel. As the core barrel is advanced, the wax seal will be pushed
along the inside of the core barrel, keeping the drilling fluids
from seeping down the core barrel or into the core. To prevent water
pressure from displacing the wax seal, formation water will be used
to fill the drill stem (from the top) thus maintaining an equivalent
water pressure inside and outside of the core barrel. The wax plug
will isolate the core from water in the core barrel and drill stem
during the coring and removal of the core.
When the core barrel is removed, the drilling water will be pumped
into the borehole to bring the water level to the top of the casing.
This will minimize the water pressure differential between the inside
and the outside of the core barrel. It will also facilitate sealing
the barrel from the atmosphere prior to removal from the well. The
core barrel will be withdrawn so that the lower end of it remains
submerged to prevent the introduction of air. When the barrel end
is just below the top of the casing, a plug of sterile modeling
clay will be packed into it to keep air from entering as it is withdrawn
from the well. The barrel will be removed and immediately placed
in the anaerobic glove box, where the air will be flushed out of
the glove box with inert gas before the ends of the barrel are opened.
Once the coring has been completed to the design depth, the hole
will be reamed to 15.4 cm in diameter using direct rotary wash techniques
with the same clean formation water used during other drilling steps.
The larger diameter will facilitate geophysical and acoustic televiewer
logging of the preliminary boreholes.
The well surface completions will be similar to other existing
monitoring wells at Pease. The 30.5 and 20-cm casings will be cut
off with the latter casing slightly below the outer casing. The
30.5-cm pipe will serve as the protective casing, and will have
a locking cap installed. In most instances, the well will be nearly
flush-mounted at the ground surface, with a relief above existing
grades of no more than 5 cm. In wooded or wetland locations, wells
will have a minimum of a 60 cm stick-up in order to readily find
them as well as prevent temporary flooding from making them inaccessible.
Tracer experiments will be conducted in the first preliminary borehole,
located in the control (uncontaminated) region, to evaluate the
potential for vertical migration of the contaminants during drilling,
in particular microbial contamination (See Section VI.C). The first
test will entail the placement of a bacterial tracer (Chromobacterium)
on top of the weathered bedrock before the first core of it is collected.
The tracer will be placed ahead of the casing and will act as a
surrogate in determining whether microorganisms found in the bedrock
are native or transported from above during drilling.
An additional tracer test will be performed where both a bacterial
tracer (INA Pseudomonas) and a chemical tracer are added to the
drilling water. The chemical tracer will be lithium bromide, in
concentrations of at least 50 ppm above the background concentrations.
The addition of tracers will occur only on the first day of competent
bedrock coring in the first preliminary borehole. Consecutive cores
of the weathered bedrock will be tested for the presence of the
chemical and bacterial tracers to evaluate vertical migration of
the tracer and /or drilling fluid contamination. The first two cores
drilled with the tracer-labelled drilling fluid will be taken without
any special drilling procedures (i.e., no wax plug or modelling
clay plug used). The cores will be analyzed for the presence of
the tracers in the fractures. The subsequent competent bedrock cores
on the first day of drilling will be retrieved using the special
handling and drilling techniques (e.g., wax plug and modeling clay
plug). These cores will be drilled using the same tracer-labeled
drilling water. Analyses of the fractures for the presence of the
tracer will provide an evaluation of the effectiveness of the special
coring procedures in isolating the core from the drilling fluids.
Drilling fluid containing only the chemical tracer will be used
for the remainder of the drilling in the first preliminary hole.
An open borehole provides an avenue where vertical migration of
contaminants may occur from contaminated fracture zones to clean
fractures. To prevent this potential migration and cross-contamination,
and still maintain the preliminary borehole for future groundwater
quality sampling or other testing, a plug will be installed in the
borehole. The plug will consist of a diffusion multi-level sampler
(DMLS), or a 10 cm PVC pipe (with flexible solvent-resistant diaphragm-type
seals) that isolates each fracture zone in a borehole. The DMLS
is a passive sampling device, containing vials with a semi- or permeable
membrane. Each vial contains sterile distilled (or deionized) and
deoxygenated water. The vials are isolated from vertical groundwater
flow in the borehole by flexible neoprene diaphragms, which seal
against the borehole wall. The modular construction with blank pipe
between devices, will allow sampling for groundwater quality from
discrete fracture zones. Over time, the membrane allows the sterile,
deoxygenated water to come into equilibrium with the water flowing
in the formation. The DMLS is removed after a discrete time, and
the water in the vial is analyzed for various chemical constituents.
The residence time needed for the vial's contents to come to equilibrium
with the formation water will be determined as outlined in Section
VI.D.
Test Boreholes in Phase III
The test boreholes will be drilled during Phase III specifically
to recover cores containing fractures, which can be used for evaluating
in situ microbial metabolic processes. The primary objective of
the drilling will be to obtain a core that has not been significantly
contaminated by microorganisms from other vertical locations in
the well. Consequently, the drilling procedure will be formulated
to prevent the introduction of microbes in the drilling fluid or
the vertical migration of microbes from the overburden or weathered
rock to the competent bedrock. At the same time, the core will be
kept under conditions similar to those that existed in situ. In
most cases, this will preclude significant exposure to air. The
procedures used in this phase of drilling will be those that were
developed and tested during the drilling of the preliminary boreholes
in Phase II.
The
test holes will be sited based on all available data gathered on
existing wells and cores, and on the data from the preliminary boreholes.
These data include the fracture density, fracture locations, and
fracture attitude. These properties will be used to site each test
borehole (presently envisioned to be within 10 meters upgradient
of the preliminary well) and also to predict the specific depths
of the fractures in each test well location (See Section VI.B).
These depths will be the target zones for coring. The test wells
will be drilled in the same zones as the preliminary wells (one
control and one in each zone of the contaminant plume: VC, DCE,
and TCE, respectively).
The drilling procedure will be similar to that used for the preliminary
boreholes, with the exception that the auger rig with continuous
sampling in the overburden will not be used. In addition, continuous
coring in the weathered bedrock will not occur. Telescoped casing
will still be used. A subcontractor, using direct rotary wash techniques,
will drill a borehole down to weathered bedrock to set and grout
a 30.5-cm casing. Clean formation water will be used as the drilling
fluid. The 30.5-cm casing will be pressure grouted into place. Once
the grout has set, the 30.5-cm casing will be drilled with an 25.4
-cm bit, and a 20 cm casing will be advanced behind the drill bit
through the weathered bedrock and at least 60 cm into competent
bedrock. The depths will be chosen based on data collected while
drilling the nearby preliminary borehole. The 20-cm casing will
be pressure-grouted into place. A 15 cm borehole will be drilled
down to the first coring zone using a roller-cone drill bit and
direct rotary wash techniques. The rotary wash will use clean formation
water from an existing well as described in Section VI.A.b.
When the desired coring depth is reached, where a fracture intersecting
the preliminary borehole is thought to intersect the test borehole,
a core will be taken using a 10-cm diameter triple-tube core barrel
with a diamond bit. The design coring depth will be established
as the depth two meters above the predicted depth of the target
fracture. The bit will leave a 14-cm diameter hole. Cores will be
taken in 1.5 meter runs. It is anticipated that this coring will
use the wax plug and modeling clay plug described previously. Each
run will be processed separately. However, this procedure may be
modified based on the results of the tracer tests performed during
the drilling of the preliminary wells.. If the procedures described
here are not as effective as required, appropriate modifications
will be made to the procedures and tested prior to the second phase
of drilling.
Each core will be extruded in the first section of the anaerobic
glove chamber, and samples will be taken for the microbiological
analyses (See Section VI.C). The atmosphere in the glove chamber
(consisting of 2 glove bags in series) will be sampled with an HNU
or OVA meter to evaluate whether organic contaminants are present.
When all microbial extraction procedures are complete, the core
will be sealed and prepared for transport to the UNH geology laboratories.
If a suitable fracture is not contained in the recovered core,
an additional run will be made, using a second sterile core barrel.
This process will continue until a satisfactory core is retrieved.
Because cores will be taken from discontinuous levels, the boring
will be reamed to a 15 cm diameter to the depth of the borehole,
and advanced to the design depth of the next core with the same
drill bit. The coring procedures will be repeated at the new level.
Test wells will be completed in a manner similar to the preliminary
wells to maintain security of the well. In-well isolation devices
(flexible diaphragm seals or DMLS devices) will be installed to
prevent vertical migration of groundwater within the well, while
still maintaining the borehole for future characterization and testing.
Drilling Parameter Recorder: Real Time Continuous
Recording
(above: typical profile)
- Depth (meters)/Penetration Rate (meters/hour)
- Rotary Speed (rpm)
- Thrust Pressure (bars)
- Hold Back Pressure (bars)
- Torque (bars)
- Drilling Water Pressure (bars)
- Drilling Water Flow Rate (liters/minute)
- Drillers Control Button
|